Implementation by Elro Net in Denmark

September 4th, 2009 No comments

From googlemap


Jan 08

Danish Utility contracts with Echelon to install NES based electricity meters to 50,000 danish homes.

Will use a variety of WAN comms solutions for backhaul including WiMAX and GPRS.

Project to run from Q4 07 to 2010

Markets:

Implementation by NRGi in Denmark

September 4th, 2009 No comments

From googlemap


Danish utility installing 52,000 Echelon meters.

Project delivery by Eltel Networks due to start in late 2008 and complete in 2011. Backend systems being provided by Gorlitz.

Markets:
Categories: 10k to 100k, AMI, Electricity, PLC Tags: , ,

Implementation in Colombia

August 22nd, 2009 No comments

From google alert

Colombian utility Empresas de Energia del Archipiélago de San Andres S.A. E.S.P. is deploying the Aclara Two-Way Automatic Communications System (TWACS) advanced metering infrastructure technology on the islands of San Andres and Providencia. The TWACS fixed-network solution transmits and receives metering and utility data over existing power lines.

16,300 meters will be installed, starting in 2009 with a target for completion by the end of 2010.

A major objective of the plan is to reduce energy losses. In the first stage, this would amount to cutting losses from 34% to 12% on two feeders. In addition, the utility wants to use the data provided by TWACS technology to eliminate estimated billing.

Markets:

Implementation by Stadtwerk Haßfurt in Germany

August 21st, 2009 No comments

From original googlemap

German utility installing 10,000 electricity meters over the next three years (complete by 2012).

EVB Energie AB will be installing Echelon’s NES PLC based system.

Click here for the press release

Markets:

Implementation by Vattenfall in Finland

August 18th, 2009 No comments

From original googlemap

Electricity company supplying 360,000 customers in Finland.

Currently 35,000 customers using L+G enermet AIM solution based on PLC to GSM concentrators.

Markets:

Implementation by Satapirkan Sähkö Oy in Finland

August 18th, 2009 No comments

From original googlemap

Satapirkan Sähkö Oy
Finnish regional electricity utility, investing 10 million Euros in a Landis+Gyr electricity smart meter solution.

The 70,000 meters will be supplied by two meter manufacturers and managed by a Landis+Gyr system.

Technology will include GPRS and PLC in urban areas, and GPRS in rural areas.

Installations will begin in 2008 and complete in 2012.

Satapirkan Sähkö Oy is a cooperative- and service company, established in 1991 and it operates in the areas of Satakunta, Pirkanmaa and Varsinais-Suomi. It owns nine local electricity companies: Kokemäen Sähkö Oy, Köyliön-Säkylän Sähkö Oy, Lammaisten Energia Oy, Lankosken Sähkö Oy, Leppäkosken Sähkö Oy, Paneliankosken Voima Oy, Sallila Energia Oy, Vakka-Suomen Voima Oy and Vatajankosken Sähkö Oy. Partner companies have all together about 120,000 customers.

Markets:

Completed implementation by PiteEnergi in Sweden

August 18th, 2009 No comments

From original googlemap

Utility serving city of Pitea.

Installed L+G AMI solution for 20,000  customers, based on LON PLC and GPRS.

Completed in 2007

Markets:

Implementation by Tornion Energia in Finland

August 18th, 2009 No comments

From original googlemap

Tornion Energia
Project to replace electricity meters at the end of their useful life with L+G enermet AIM smart meters.

11,000 meters that will work with a combination of PLC and GPRS

Markets:

Implementation by Kemin Energia

August 18th, 2009 No comments

From original googlemap


Kemin Energia supplies electricity and district heat to 14,700 customers in Kemi.

Kemin Energia is to implement smart metering into 15,000 households to improve its meter reading and invoicing processes and also improve customer service.


Categories: 10k to 100k, AMI, Electricity Tags:

Implementation by Kainuun Energia in Finland

August 18th, 2009 No comments

From original googlemap

Kainuun Energia

Electricity company serving 55,000 customers.

Installing L+G enermet AIM solution based on PLC with GPRS, due to complete in 2008

Markets: